New construction of a multifunctional house with fire station
The multifunctional house has a full basement and has two floors (ground floor and upper floor), this part of the building is built in masonry construction with
prestressed reinforced concrete slabs.
Adjacent to the multifunctional house is the fire brigade equipment house, which is to be built in steel construction. The building envelope (walls and ceilings) of the
Fire station is to be clad with sandwich panels.
Multifunctional house and fire station have a flat pitched monopitch roof.
Between the multifunctional building and the fire brigade equipment house there is a single-storey connecting building in solid construction, with a
walkable flat roof.
Dimensions of the individual parts of the building:
Multifunktionshaus ca. 17m x 28m
Intermediate construction approx. 5m x 12m
Fire station approx. 28m x 20m
New multifunctional building with fire station
STAHLBAUARBEITEN FEUERWEHRHALLE
FIRE STATION AREA
Steel construction made of typified steel profiles approx. 32 tons
Wall construction made of sheet metal cassettes approx. 550 m²
Mineralwolldämmung ca. 550 m²
Aluminum façade panels approx. 550 m²
Roof structure made of sandwich panels approx. 675 m²
Coating steel profiles approx. 32 tons
Gerüststellung ca. 790 m²
AREA FIRE STATION Canopy
Steel construction made of typified steel profiles approx. 8 tons
Untersichtsverkleidung ca. 120 m²
trapezblechtragschale ca. 120 m²
Stahlprofile feuerverzinken ca. 8 to
AREA OF THE FIRE BRIGADE HALL Metal construction windows and doors
Aluminum frame door elements approx. 5 pcs
Aluminium window strips approx. 17.4m x 1m
Sheet steel doors approx. 12 pcs
Fire Brigade Steel Folding Gates 4 pcs