General planning services for new buildings and technical equipment according to HOAI
Construction of a new substation for two, possibly three 110/10 kV transformers with 40 MVA output, an electric coil and an air-insulated MV system as well as a 110 kV plant SF6.
The following planning services are required:
- Object planning building according to § 34 HOAI 2021
- Object planning of outdoor facilities according to § 39 HOAI 2021
- Structural planning according to § 51 HOAI 2021
- Technical equipment electrical engineering according to § 55 HOAI 2021
- Technical equipment planning HLS according to § 55 HOAI 2021
- Specialist planning of technical equipment building management systems according to § 55 HOAI 2021
- Specialist planning Technical equipment Conveyor systems according to § 55 HOAI 2021
- Building physics according to Annex 1 Point 1.2.2 HOAI 2021
- Fire protection according to AHO, issue 17
- SIGEKO