The city of Essen is planning the construction of another school building on the school grounds of André-
asschule, Von-Einem-Straße 56 in Essen. For this purpose, the building Pavilion 1 is to be dismantled and
to construct a new excavation pit.
The existing building (pavilion 1) is to be dismantled, including floor slabs and foundations. Of
Furthermore, partial surface sealing, enclosures, lanterns, etc.
can be removed. In the run-up to the measure, a pollutant report was carried out by GeoID.
(see Appendix II). Applications containing harmful substances (asbestos/KMF/PAH)
Found. In addition, a sampling of the roof and further investigations of the roof were carried out.
Building by Mull und Partner Ingenieurgesellschaft mbH. The pollutant-relevant emissions
Results are given in Table 1 under Title 2 and the additional analysis results in the Appendix
II. These pollutants must be professionally removed before the actual dismantling activities begin.
just to remove.
In the course of the new building planning, a subsoil investigation was carried out. The opinion is
Annex VI (Hinz Ingenieure).
The work must be carried out within a maximum of 6 weeks.
The present call for tenders includes:
- clearing out and gutting of the building,
- the remediation of applications containing asbestos, CMF,
- dismantling including deep debris,
- clearance of enclosures, lanterns, etc. on the outdoor area,
- Open space unsealing (tar-stemmed PAH), incl. substructures and fillings
- the creation of a construction pit with embankments
The disposal / recycling of all waste must be carried out by the contractor. The eANV is carried out
By the AN.
2 LOCATION
The exact location of the school and the building to be dismantled, including access road and installation area, is the
The construction fences are shown in the plan of Annex I. The access road to the site leads through residential
areas with sometimes very cramped road conditions. The public passability of the Odastraße
and the Von-Einem-Straße must be guaranteed at all times during the dismantling project.
The cordoning off of the construction site takes place in the northern area in the schoolyard, which is also open during
of the dismantling work is used by the students. The southern area with the access road will be
not used by the school.
See LV