Replacement of the bank surrounds with sheet piling walls and embankment
in the area of CVK km 0.600 - km 1.300
The bank surrounds on the Charlottenburg connecting canal are dilapidated and must therefore be replaced.
The CharlottenburgEr Verbindungskanal (CVK) is a federal waterway serving general traffic within the meaning of the WaStrG of waterway class IV and is assigned to the secondary network of federal inland waterways.
The banks of the CVK have numerous damaged areas and are in need of repair. They are therefore to be renewed in the range CVK-km 0 to CVK-km 1.3.
For this purpose, the canal will be divided into two construction phases, which are to be realized at a staggered time. The first construction phase ranges from kilometer 0.600 to kilometer 1.300 and is to be awarded herewith.
The following essential services are to be awarded:
- Landscaping incl. tree felling
- ordnance clearance
- dismantle and dispose of approx. 2,000 m3 of inclined bank fastening
- approx. 1,700 m3 of soil loosen and temporarily store
- approx. 16,350 m3 of dredging including interim storage on barges
- install and compact approx. 2,900 m³ of soil
- deliver approx. 2,100 t sheet piling walls
- bring in approx. 14,800 m² sheet piling walls
- shorten approx. 835 m sheet pile wall in the water area
- approx. 110 pcs of continuous grouting anchor including connections
- produce approx. 650 m cover spar
- All planning services for the execution and inventory documents