22S051057 BPOL FLS FUD GF - New construction: LB TA-M (new)
New construction project of the federal government - GNUE
New building Accommodation of the Federal Police - Fliegerstaffel Fuhlendorf am Standort Gifhorn (BPOL FLS FUD)
Planning Services TA M according to § 53ff HOAI 2021
for KG 410-430, 470, 480 (DIN 276),, performance phase 3 (4)
(EW-Bau) with option of further commissioning of Lph 5-8
After the arrival of several hundred Federal Border Guard officers in March 1959, the Gifhorn location experienced an eventful history: closed in 1999, reactivated in 2005. In April 2007, the decision was made for a final dissolution.
In 2012, the BMI user department decided to maintain the service location with the base of the Federal Police Air Squadron in Gifhorn in the long term.
As a result, the first modernization measures, such as renewal of the hall apron, refueling system, guard building, were initiated. At the same time, property areas not required by the Federal Police were returned to the owner (Federal Institute for Real Estate - BImA) and sold by her.
In a letter from the Federal Agency for Real Estate, the supervisory examined decision document Construction (ES-Bau) for the construction project:
"New accommodation of the Federal Police Air Squadron Fuhlendorf (BPOL FLS FUD) at the Gifhorn base"
Submitted to the BMI for planning approval and setting of a cost ceiling. The service property is part of the Unified Property Management (ELM) and thus owned by the Federal Institute for Real Estate (BImA).
The object of the construction project is the construction of the new office building, a hangar for police helicopters with a new tower, a motor vehicle hangar and the preparation of the existing helicopter hangar for special situations, including expansion of the hall apron.
This is intended to create the conditions for the additional tasks of the Federal Police Fuhlendorf at the Gifhorn base, which go hand in hand with additional space requirements and personnel growth.
The conversion of the property will take place in the unrestricted service and flight operations of the Federal Police (BPOL).
The total construction costs of KG 200-600 according to DIN 276 in the measure amount to EUR 40,383,451.50 gross. The costs for the respective plant groups that can be charged for the tendered service profile TA-Elt are
- cost group 410 = 452,650 EUR gross
- cost group 420 = 1,432,242 EUR gross
- cost group 430 = 585,586 EUR gross
- cost group 470 = 18,000 EUR gross
- cost group 480 = 600,000 EUR gross
These do not include risk costs and correspond to the funds recognised by the BMF. Cost groups 420 and 430 include pro rata costs from cost groups 540, insofar as these are not attributable to civil engineering structures.
The services to be commissioned "TA-M" of this procedure are described in more detail below. Bidders are requested to address any queries to the client via the award platform by 28.04.2023 at the latest. Questions received after 28.04.2023 will no longer be answered.
The existing infrastructure on the property such as RW and SW sewer, drinking water pipe, heat supply network, entire electrical supply, etc. are to be regarded as obsolete due to age. Due to the planned demolition measures of buildings and the associated traffic areas, almost all parts of these supply networks are no longer necessary. In addition, due to the separation of the property, the individual systems can no longer be used. The buildings 8-10 must be able to be operated continuously during the construction project, for this a supply of the technical media is necessary and, if necessary. a supply concept for the construction period is to be created.
The following services are required in the field of
Technical equipment:
- Creation of a property-related energy supply concept for the new buildings to be constructed for both heat and electrical supply in accordance with the GEG. In the ES-Bau reference is still made to the EEWärmeG. In this context, the heat supply solution developed in ES-Bau must be evaluated with regard to a legally compliant implementation possibility.
- The technical equipment of the four buildings to be constructed must be planned according to the use on the basis of the ES construction, the approved space program and in accordance with the applicable standards. The security aspects of the Federal Police as a security authority must be taken into account in security of supply and burglary protection.
- In cooperation with the project controller, a technical monitoring must be set up and a coordinated commissioning of the property must be provided.
- The hangars for aircraft maintenance will have to be equipped with retractable PIT supply systems, which will have to be taken into account in the TA-Elt contract under cost group 470.