Renewal and modernization of the Bühlot outdoor pool in Bühlertal:
After more than 50 years of operation, the outdoor swimming pool built in the 1960s is in need of major renovation and modernization.
The following measures are planned:
- Reduction of the water surface of the existing combination pool from approx. 1,500 square meters to 960 square meters,
- Dismantling of the existing functional building and replacement with a two-part new building with accommodation of the technical systems as well as the changing, sanitary and personnel areas,
- Complete renewal of the water treatment system and the associated piping as well as renewal of the sanitary, heat supply and electrical systems,
- Installation of a stainless steel combination pool in the existing concrete pool,
- complete renovation of the outdoor facilities,
- Installation of a wide wave slide and a new jumping facility (1 m, 3 m, 5 m).
Start of construction: March 1, 2021 Completion: April 15, 2022 Total construction costs (KG 200-600): approx. 5.6 million EUR net.
High and low voltage systems:
- 1 piece main distribution,
- approx. 160 pieces of lights,
- 2 mast lights,
- Site electricity / dismantling work,
- inlay work,
- KNX building automation,
- 1 group battery system,
- approx. 4 800 m power lines,
- approx. 7,000 m of low-voltage lines.
Period:
- Site electricity / dismantling 1.3.2021,
- Inlay work from October 4th, 2021,
- Electrical installation October 4, 2021 to March 14, 2022,
- Commissioning until April 30th, 2022,