Process Control and Information System for the power plant Amagerverket Unit 3
The Power Plant Amagerverket unit 3 in Copenhagen will be rebuild for 100 % wood pellets. In this context the existing DCS has to be replaced. The work comprises development, engineering, production, installation and test of a integrated plant control system.
The full integrated system must include:
Process Control and Information System for controlling the boiler, flue gas system and other auxiliary systems.
Turbine control and protection system.
Boiler protection system in Fail-Safe technology.
Graphical HMI (Human Machine Interface) for multiple operators.
A common engineering platform from which the entire integrated plant control system can be engineered.
Database for logging data. The database should be accessible for other applications.