Construction of 4 6-storey residential buildings with 10 apartments each with a total living area of approx. 3 400 m
Gross amounts:
- own construction site facility:
- BE for own construction services, incl. TDK,
- About 700 m
- earthworks:
- about 1250 m
- Analysis according to LAGA by AG,
- remove and dispose of approx. 1 280 t excavation excavation,
- of which approx. 1 000 t disposal allocation class up to Z2,
- of which approx. 800 t disposal allocation class> Z2,
- about 750 m
- deep foundations / large bored piles:
- 380 m hole for large bored pile diam. Approximately Produce 900 (880) mm,
- approx. 220 m concreting / in-situ concrete C30 / 37 for large bored pile diam. Approximately Install 900 (880) mm,
- deliver and install approx. 15 t of reinforcing steel for reinforcing steel,
- Stake approximately 57 pieces of pile heads approx. 50 cm.
- drainage channel works:
- about 250 m excavation pit in and outside building, depth up to 80 cm,
- about 50 m
- approx. 250 m laying of new underground pipes PP pipe up to DN 150, outside and in the building,
- Install approx. 30 pieces of built-in elements in floor panels.
- reinforced concrete works foundation:
- about 265 m
- About 150 m
- about 590 m
- Deliver and install approx. 75 t of reinforcing steel for foundations.
- reinforced concrete works
- about 300 m
- About 2 400 m
- deliver and install approx. 45 t of reinforcing steel for walls,
- About 100 m
- about 300 m
- about 2000 m
- about 380 m
- deliver and install approx. 100 t of reinforcing steel for monolithic and semi-finished slabs,
- Supply and install various punching shear reinforcement.
- reinforced concrete prefabricated parts:
- manufacture, deliver and assemble 20 pieces of prefabricated staircases with 2 podiums,
- Produce, deliver and assemble 16 pieces of balcony sheets up to approx. 2.20 x 3.40 m.
- masonry work:
- about 1 700 m
- Sealing and insulation work:
- about 220 m