BBZ Heide, new building Berufsbildungszentrum_VE 08 Metalworking
The gross floor area (BGF) is approx. 7,800 m 2 and the gross volume (BRI) is approximately 36 700 m 3 ,
Construction began in January 2019.
The planned total construction time is 20 months.
Supply and installation of triple-glazed and anodized light-metal facade elements, consisting of:
Approximately 1 100 m 2 Window and door elements approx. 400 m 2 Post and beam facade about 650 m 2 Blinds (external blinds) approx. 450 m Fenced benches approx. 170 m 2 Ventilation fins for night cooling.