Construction of container modular buildings for school use as an interim at various locations in the city
Locations 1 + 3: - Location 1: Grundschule Bedingrade, Bergheimer Str. 67, 45359 Essen - Location 3: Schule am Reuenberg, Reuenberg 163, 45357 EssenConstruction of modular container buildings for school use as an interim at various locations in the city.
Manufacture, delivery and assembly of system containers in accordance with the Building Energy Act (GEG) as purchase containers. The container modular buildings serve as an extension of existing school locations
with increased space requirements. Key data: 10 pieces
1-storey container facility with 4 classrooms
BGF ca. 398 m2
Thermal insulation according to GEG
Additional roof as monopitch roof
Construction of pipeline trench for media route
Execution immediately after commissioning.
Dates locations 1, 3, 4, 5, 7, 9:
Construction of media route, drainage: 17.07. - 04.08.2023 (within NRW summer holidays)
Installation of containers: 02. - 13.10.2023 (within NRW autumn holidays)
Completion incl. all acceptances: 15.12.2023
Nutzungsbeginn: 08.01.2024
Dates locations 2, 6, 8:
Construction of media route, drainage: 02. - 13.10.2023 (within NRW autumn holidays)
Container installation: 13. - 28.11.2023
Completion incl. all acceptances: 16.02.2024
Nutzungsbeginn: 04.03.2024
It is a functional tender, divided into 5 lots of 2 system pavilion
Execution immediately after commissioning.
Container installation and start of use: as soon as possible
Location 2: Junction Schule am Steeler Tor, Altenbergstr. 12, 45141 EssenConstruction of modular container buildings for school use as an interim at various locations in the city.
Manufacture, delivery and assembly of system containers in accordance with the Building Energy Act (GEG) as purchase containers. The container modular buildings serve as an extension of existing school locations
with increased space requirements. Key data: 10 pieces
1-storey container facility with 4 classrooms
BGF ca. 398 m2
Thermal insulation according to GEG
Additional roof as monopitch roof
Construction of pipeline trench for media route
Execution immediately after commissioning.
Dates locations 1, 3, 4, 5, 7, 9:
Construction of media route, drainage: 17.07. - 04.08.2023 (within NRW summer holidays)
Installation of containers: 02. - 13.10.2023 (within NRW autumn holidays)
Completion incl. all acceptances: 15.12.2023
Nutzungsbeginn: 08.01.2024
Dates locations 2, 6, 8:
Construction of media route, drainage: 02. - 13.10.2023 (within NRW autumn holidays)
Container installation: 13. - 28.11.2023
Completion incl. all acceptances: 16.02.2024
Nutzungsbeginn: 04.03.2024
It is a functional tender, divided into 5 lots of 2 system pavilion
Execution immediately after commissioning.
Container installation and start of use: as soon as possible
Locations 4 + 6: - Location 4: Eichendorffschule, Heißener Str. 74, 45359 Essen - Location 6: Helmut-Rahn-Realschule, Mülheimer Str. 126, 45145 EssenConstruction of modular container buildings for school use as an interim at various locations in the city.
Manufacture, delivery and assembly of system containers in accordance with the Building Energy Act (GEG) as purchase containers. The container modular buildings serve as an extension of existing school locations
with increased space requirements. Key data: 10 pieces
1-storey container facility with 4 classrooms
BGF ca. 398 m2
Thermal insulation according to GEG
Additional roof as monopitch roof
Construction of pipeline trench for media route
Execution immediately after commissioning.
Dates locations 1, 3, 4, 5, 7, 9:
Construction of media route, drainage: 17.07. - 04.08.2023 (within NRW summer holidays)
Installation of containers: 02. - 13.10.2023 (within NRW autumn holidays)
Completion incl. all acceptances: 15.12.2023
Nutzungsbeginn: 08.01.2024
Dates locations 2, 6, 8:
Construction of media route, drainage: 02. - 13.10.2023 (within NRW autumn holidays)
Container installation: 13. - 28.11.2023
Completion incl. all acceptances: 16.02.2024
Nutzungsbeginn: 04.03.2024
It is a functional tender, divided into 5 lots of 2 system pavilion
Execution immediately after commissioning.
Container installation and start of use: as soon as possible
Lot IV: Locations 5 + 7: Location 5: Realschule im Bezirk Zollverein, Gelsenkirchener Str. 138, 45309 Essen - Location 7: Glückauf-Schule, Bischoffstr. 120, 45329 EssenConstruction of modular container buildings for school use as an interim at various locations in the city.
Manufacture, delivery and assembly of system containers in accordance with the Building Energy Act (GEG) as purchase containers. The container modular buildings serve as an extension of existing school locations
with increased space requirements. Key data: 10 pieces
1-storey container facility with 4 classrooms
BGF ca. 398 m2
Thermal insulation according to GEG
Additional roof as monopitch roof
Construction of pipeline trench for media route
Execution immediately after commissioning.
Dates locations 1, 3, 4, 5, 7, 9:
Construction of media route, drainage: 17.07. - 04.08.2023 (within NRW summer holidays)
Installation of containers: 02. - 13.10.2023 (within NRW autumn holidays)
Completion incl. all acceptances: 15.12.2023
Nutzungsbeginn: 08.01.2024
Dates locations 2, 6, 8:
Construction of media route, drainage: 02. - 13.10.2023 (within NRW autumn holidays)
Container installation: 13. - 28.11.2023
Completion incl. all acceptances: 16.02.2024
Nutzungsbeginn: 04.03.2024
It is a functional tender, divided into 5 lots of 2 system pavilion
Execution immediately after commissioning.
Container installation and start of use: as soon as possible
Locations 8 + 9: - Location 8: Parkschule, Tiefenbruchstr. 20, 45326 Essen - Location 9: Junction Maria-Wächtler-Gymnasium, Isenbergstr. 77, 45130 EssenConstruction of modular container buildings for school use as an interim at various locations in the city.
Manufacture, delivery and assembly of system containers in accordance with the Building Energy Act (GEG) as purchase containers. The container modular buildings serve as an extension of existing school locations
with increased space requirements. Key data: 10 pieces
1-storey container facility with 4 classrooms
BGF ca. 398 m2
Thermal insulation according to GEG
Additional roof as monopitch roof
Construction of pipeline trench for media route
Execution immediately after commissioning.
Dates locations 1, 3, 4, 5, 7, 9:
Construction of media route, drainage: 17.07. - 04.08.2023 (within NRW summer holidays)
Installation of containers: 02. - 13.10.2023 (within NRW autumn holidays)
Completion incl. all acceptances: 15.12.2023
Nutzungsbeginn: 08.01.2024
Dates locations 2, 6, 8:
Construction of media route, drainage: 02. - 13.10.2023 (within NRW autumn holidays)
Container installation: 13. - 28.11.2023
Completion incl. all acceptances: 16.02.2024
Nutzungsbeginn: 04.03.2024
It is a functional tender, divided into 5 lots of 2 system pavilion
Execution immediately after commissioning.
Container installation and start of use: as soon as possible