As part of the reconstruction of the main road and the adaptation of light rail stops through the conversion into three elevated platforms, moBiel GmbH intends to adapt or build 6 new traffic lights at the same time.
The offer includes the delivery and installation of the six above-mentioned traffic light systems as part of the funded construction project.
An empty conduit and shaft system is largely created by the road/track construction company.
However, this must be supplemented in parts.
The placement of the plant accessories takes place after specification of the construction supervision.
The applicable guidelines and regulations shall apply. The calculation shall take into account the fact that a complete, operational system must be supplied and installed, even if not all the parts required for technical interaction are listed and described in detail.
The control unit of the traffic light systems (LSA) must correspond in its technical design and in its functional sequence to the form approved by the city of Bielefeld.
Control unit types that have not yet been used by the city of Bielefeld must be presented to the city of Bielefeld in Bielefeld as part of the evaluation and approved jointly.