The object of the order is the construction of a water supply network in Greater Poland — north side, which includes:
— water supply from pipes with a diameter of DN150 mm, approximately 105,50 mb in length for open excavation in accordance with the design,
— water supply from pipes with a diameter of DN150 mm, of a length of approximately 830,00 mb to be performed by a trenchless method in accordance with the design,
— a protective pipeline of pipes with a diameter of Φ 355/28.6 mm, with a length of approximately 31,50 mb to be performed by a trenchless method in accordance with the design,
— making reinforcement of the ground substrate by injecting dispersion at selected nodes in accordance with the design,
— siltation of an existing (decommissioned) network of approximately 940 mb length and dismantling of existing armament components for the decommissioned network as designed,
— 18 pcs of water supply connectors (10 pcs for replacement, 7 per surge, 1 pcs new) according to the design, including:
— the execution of roadworks, for demolition and reproduction of pavement,
— the marking of investments.
The object of the order is the construction of a water supply network in Greater Poland — north side, which includes:
— water supply from pipes with a diameter of DN150 mm, approximately 105,50 mb in length for open excavation in accordance with the design,
— water supply from pipes with a diameter of DN150 mm, of a length of approximately 830,00 mb to be performed by a trenchless method in accordance with the design,
— a protective pipeline of pipes with a diameter of Φ 355/28.6 mm, with a length of approximately 31,50 mb to be performed by a trenchless method in accordance with the design,
— making reinforcement of the ground substrate by injecting dispersion at selected nodes in accordance with the design,
— siltation of an existing (decommissioned) network of approximately 940 mb length and dismantling of existing armament components for the decommissioned network as designed,
— 18 pcs of water supply connectors (10 pcs for replacement, 7 per surge, 1 pcs new) according to the design, including:
— the execution of roadworks, for demolition and reproduction of pavement,
— the marking of investments.