B180 village bypass Aschersleben-Süd/Quenstedt
Lot 4.2_B180, new building BW 4A (0898), bridge over the L 229 and manufacturing of a construction road to BW 5UE.
The following key benefit is included in the tender:
— topsoil removal 3 386.00 m³,
— cover topsoil 230.00 m³,
— loosen soil 1 996.00 m³,
— delivery floor 2 420.00 m³,
— floor exchange 230.00 m³,
— lay geotextile 4 600.00 m²,
— cleanliness layer 270.50 m²,
— concrete for foundations 250.00 m³,
— concrete for substructures 470.00 m³,
— concrete for superstructure 260,00 m³,
— concrete for towplates 40.00 m³,
— concrete for caps 60.00 m³,
— make railings 118.00 m,
— milling asphalt 1 615.00 m²,
— absorb layers without binder 170.00 m³,
— produce antifreeze layer 1 300.00 m³,
— produce gravel base layer 900.00 m³,
— produce asphalt surface layer 220.00 m²,
— produce asphalt binder layer 90.00 t,
— Produce asphalt topcoat 550.00 m².