See II.1.1
Project line No. 1:94 log. Ind. City of Bonniers II in BAUDOURThese are individual cadastral dwellings on two levels, 3 fronts with garage
(semi-open order) built in 1978 located in the city of Bonniers II in 7331 Baudour.
There have been no subsidized projects; at present work on its own background for the
replacement of exterior carpentry (file 123710).
Overall, the electrical and gas installation are compliant. Nevertheless, it could be
that, from time to time, this is not the case. For these situations, a budget has been set aside in
the renovation plan.
The current ventilation system is compliant and type C (natural air supply and
mechanical extraction).
Some of the houses targeted in this project line have a production of DHW on the
boiler, the other has an electric boiler independent of the heating system. It is
also provided electric boilers by handing over the production of DHW on the gas boiler
existing. A centralized extraction will be installed.
There is currently no insulation on the floor. Since the houses are built on the ground, it
will not be possible to insulate this wall.
The current label is established in F/E The projected label will be in B after work (SEE PJ). The
projected certificate does not take into account the renovation of the entire envelope (gold
all the walls will be insulated), so it will be better than the one announced.
Project line No. 12:36 collective logs. Rue d'Herchies and du BonThese are cadastral (eligible) dwellings (see Abyla 0258C035) of collective type of six
blocks of six dwellings built in 1965 located at Rue d'Herchies and Bon Logis.
There were no subsidized projects.
Currently, the dwellings have an electrical installation and a gas installation.
compliant. The dwellings have a type C ventilation system.
central heating with a collective condensing gas boiler. The ECS is produced by
an electric boiler. A production of DHW is provided via an exchanger-tank connected to
the boiler.
The planned works are the insulation of the facades via a coating on insulation, the replacement
exterior carpentry taking into account the ventilation system (system C) and
the insulation of the ceilings of the floor.
The current label is established in F/G The projected label will be in B after work (see P.J.)
Project line No. 13:6 log. Ind. TERTRE Shores PasturesThese are (eligible) cadastered dwellings (2205I), individual and adjoining type (semi order).
opened) built in 1955 located at Rue des Pâtures Rivages in Tertre
There were no subsidized projects.
Currently the electrical installation and the gas installation are in compliance. If
punctually this was not the case, we would activate our stock market. The buildings have
a type C ventilation system. They are equipped with gas central heating
including a condensing boiler with direct DHW production.
The planned works are the insulation of the envelope (floor, walls and roof) and the repair of the
roofing.
The current label is established in F. The projected label will be in B after work (see P.J.)
Project line 4:29 log. Ind. Rue de la Quietude in BAUDOURThese are small (eligible) cadastered dwellings (see E.A. Abyla 0259E001) type
individual on one level with a flat roof and built in 1981 located at the
Rue de la Quietude in 7331 Baudour.
Currently, the dwellings are equipped with a type C ventilation system, a
gas central heating with direct DHW production.
As the rental rehabilitations of our management, the gas installations and
electricity will be carried out via a specific market.
Since the houses are built on the ground, it is not possible to insulate the ground.
There were no subsidized projects.
A permit will be introduced with DGO4 for the repair of the envelope.
The current label is established in G. The projected label will be in B after work
Project line 5:14 log. Ind. Second Street in SAINT-GHISLAINThese are cadastral (eligible) dwellings (Abyla 2214A009) individual type out of two
levels with a full basement giving access to the garden, grouped in blocks of 2 or
4 houses (see location) built in 1952 located at Rue Deuin 7330 St Ghislain.
There were no subsidized projects.
In order to stay within the overall envelope of the renovation plan and complete the renovation
of the 2
th street, we would carry out the envelope work within the framework of the plan. We would isolate
all the walls (floor with basement insulation on the underside, wall with plaster on
insulation and roofing). The entire roof would be redone, a skylight would be provided for
have a sufficient escape for access to the attic room. So that the system
ventilation system is complete, a type C+ system would be installed.
A building permit will be introduced (insulation and plastering on existing walls) by a
outside service provider. Central heating including a gas-fired condensing boiler
with direct DHW production. Electrical compliance will also be achieved.
The current label is established in G/F The projected label will be in B after work (see P.J.).
The projected label only takes into account the insulation of the gables but we would realize the insulation
of all the walls (so the label will be better than the one announced).
Project line 6:8 log. Ind. Rue des Pâtures Rivages in TertreThese are (eligible) cadastral dwellings (Abyla 2205CA06) individual type
composed of a block of 8 semi-detached houses spread over two levels (one
accommodation by level) each with their own garage and their private entrance. These
housing located in Rue des Pâtures Rivages in 7333 Tertre date from 1980 and
have two bedrooms.
There was a subsidized project for 18 of the 26 housing units on the street.
Currently these homes have a type C ventilation system and
gas central heating with direct DHW production. The boilers of
our fleet are new, they are gradually replaced in such a way
that our entire fleet is always up to date. The electrical installations of
these homes are to be reviewed, the gas installations are up to standard, the roof
is dilapidated.
The housing is built on vacuum-ventilated but the complexity of accessibility does not
will not allow you to isolate the ceiling from these voids.
It provides for the insulation of walls (with plaster on insulation), the replacement of
joinery (while remaining compliant with the ventilation system in place), the
replacement and insulation of the roof and the compliance of the installation
electric. As for the roof, it contains asbestos, prices
in the budget include the treatment of this waste
The label of housing left in the state is established in G. The projected label will be in B
after work (see P.J.)
Project line 7:20 log. Ind. Street of Sglatignies, StambruggeThese are cadastral (eligible) dwellings (Abyla 2197A010) of individual type and
semi-detached (semi-open order) built in 1978 located Rue de Sglatignies,
Stambrugge and Mr. Dumont in Neufmaison.
There were no subsidized projects, only work on own funds
for the installation of new PVC boilers and exterior joinery.
The dwellings currently have oil-fired boilers (replaced in
2013) as well as PVC frames (dating back less than 20 years). The system of
ventilation is complete and type C. The accommodations are on the ground, we
do not have the ability to insulate the floor.
The planned works are the entire insulation of the facades, the repair and the insulation
slate roofs. Electrical compliance will also be
carried out as part of the renovation plan, as well as the installation of a
centralized extraction. As far as roofs are concerned, these contain
asbestos. Estimated prices include asbestos treatment.
The label established in 2020 is in D (new chassis and boilers). The label
projected is C (SEE PJ) because it does not take into account the laying of a plaster on
insulation on all facades, with this work we are aiming for a B label.
Project line 8:16 log. Ind. City Wauters in TERTREThese are small (eligible) cadastered dwellings (see E.A. Abyla 2207A200)
single-storey individual type with a slate gable roof
artificial, built in 1980 Located in the City Wauters in Tertre.
There were no subsidized projects.
Currently, the accommodations are not insulated, they are equipped with heating
electric, an electric boiler, a type C ventilation system.
The electrical installation is supposed to be compliant. When it is not, it
is rehabilitated by our management during renovations.
The city of Wauters is not served by city gas. Given the little ground
available and since there is often no direct access to the garden, it is
you can't put a tank on gas. Given the small size of the dwellings, a
local heating is sufficient, that's why we are heading to the
pellet.
Regarding domestic hot water, the only option available to us is
electric boiler that we compensate with photovoltaic panels.
We don't have the space available to put a DHW production by
solar panels or via a thermodynamic boiler.
We plan to insulate all the facades, redo the roofs (and
isolate them) and replace the joinery (respecting the
ventilation). Since the houses are built on the ground, it will not be
possible to insulate the floor.
The current label is established in G. The projected label will be in B after work (see
P.J.)
Project line No. 9:4 log. Ind. Rue des Fir trees in BAUDOURThese are (eligible) cadastral dwellings (0258A005) individual and adjoining type (order
semi-open) built in 1979 located at Rue des Sapins in Baudour.
There were no subsidized projects.
Currently, the dwellings are equipped with gas central heating with production
direct from DHW. They have a type C ventilation system.
outsides are obsolete. The walls are not insulated. Electricity is compliant, if we
findings of a problem, we would punctually activate our stock market for the
bring it back into compliance.
We plan to insulate the entire envelope. A coating on insulation will be carried out, a
insulation will be placed in the basement on the underside, the exterior carpentry will be replaced in
taking into account ventilation and the ceiling of the floor will be insulated and tile cover
will be replaced. A centralized extraction system will also be installed (system
C+).
The current label is established in G/F The projected label will be in B after work (see P.J.)
Project line No. 10:33 log. Ind. City of Chaufours in HAUTRAGEThese are (eligible) cadastered dwellings (2201A001) individual and semi-detached type (order
semi-open) built in 1979 located at the City of Chaufours in Hautrage.
There were no subsidized projects.
Currently, the dwellings are equipped with a non-compliant ventilation system
(mechanical extractions present, no air inlets), they are equipped with a boiler
with condensing gas with direct DHW production. The electrical installations are
up to standards. Occasionally, if necessary, we would activate a stock market for
the electrical or gas compliance and our teams (Régie Ouvrière) would install one or
the other missing extractor.
The planned work is the complete renovation of the envelope with the exception of the floor
(houses on land, no technical possibility to insulate the ground). A coating on insulation
and insulated siding is provided for the elevations. The roofs will be replaced and
isolated. New exterior carpentry taking into account air intakes (in order to
make housing compliant from a ventilation point of view) will be installed.
The current label is established in G/F The projected label will be in B after work (see P.J. LTF).
Project line No. 11:18 collective logs. O. Gilmant Street in TERTREThese are cadastral (eligible) housing (see Abyla 2203C02) of collective type of two
blocks built in 1965 located at O. Gilmant Street in Tertre.
There were no subsidized projects.
Currently the dwellings are equipped with collective gas boilers (1/building). The
ventilation system is a type A system. Electricity and gas installation is
compliant.
The planned work is the insulation of the envelope with the exception of the floor by making a
coated on insulation. New joinery in line with a ventilation system of type
C will be installed. The insulation and waterproofing of flat roofs will be fully
journals. Extractors in wet rooms can be installed independently
by our workers' management or by a totally independent market carried out in parallel.
The current label is established in F/G The projected label will be in B after work (see P.J.)