General project management for the extension of tram line 1 to Montpellier Sud de France station. The EOC will be asked for a critical appropriation/analysis of the AVP phase carried out by the current EM + standardized project management missions:
- Project studies (Pro);
- Assistance with works contracts (ACT);
- Execution studies (EXE);
- Visa (VISA);
- Direction of the execution of works (DET);
- Assistance to reception operations (AOR).
+ Complementary missions:
— Synthesis cell direction (SYN);
— Mastery and coordination of construction sites (MCC);
— coordination and travel of Third Party Networks (RES);
— Establishment of Security Records (SECU);
— Carrying out the overall tram tests (EET).
Envelope works: 21 820 000 EUR excluding VAT (value January 2021).
General project management for the extension of tram line 1 to Montpellier Sud de France station. The EOC will be asked for a critical appropriation/analysis of the AVP phase carried out by the current EM + standardized project management missions:
- Project studies (Pro);
- Assistance with works contracts (ACT);
- Execution studies (EXE);
- Visa (VISA);
- Direction of the execution of works (DET);
- Assistance to reception operations (AOR).
+ Complementary missions:
— Synthesis cell direction (SYN);
— Mastery and coordination of construction sites (MCC);
— coordination and travel of Third Party Networks (RES);
— Establishment of Security Records (SECU);
— Carrying out the overall tram tests (EET).
Envelope works: 21 820 000 EUR excluding VAT (value January 2021).