The subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021). The project is co-financed by the Cohesion Fund under the Infrastructure and Environment Operational Programme 2014-2020 Priority Axis I Reducing the emissivity of the economy, Action 1.7 Comprehensive elimination of low emissions in the Silesian province Subaction 1.7.2 Effective distribution of heat and cooling
In Silesian Voivodeship.
The item of the order was divided into parts.
The scope of construction works includes the construction of approximately 2,205.0 m of district heating networks and the construction of 35 heat nodes.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part AThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part A includes the task: Z6A.1, Z6B.1 “Attachment to the district heating network of buildings in the area of Orzeszkowa Street and Rejtana Street in Bytom”.
The scope of construction works includes the construction of district heating networks approx. 122.7 m and the construction of 3 heat nodes;
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part JThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part J includes the task: Z6A.13, Z6B.13 “Attachment to the district heating network of the building at 63 Constitution Street, Constitution 65 in Bytom”.
The scope of construction works includes the construction of a heating network of approx.170.0 m and the construction of 2 heat knots
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part KThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part K includes the task: Z6A.14, Z6B.14 “Attachment to the district heating network of the building at 36 Armia Krajowa Street in Bytom”.
The scope of construction works includes the construction of a district heating network approx. 5.50 and the construction of 1 heat node
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part LThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part L includes the task: Z6A.15, Z6B.15 “Connection to the district heating network of the building at 8 Romanowski Street in Bytom”.
The scope of construction works includes the construction of a district heating network of approx.31.5 m and the construction of 1 heat node
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part MThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part M includes task:Z6A.16, Z6B.16 “Connection to the district heating network of the building at 1,3,5 Zieliński Street in Bytom”.
The scope of construction works includes the construction of a district heating network of approx.31.0 m and the construction of 1 heat node
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part NThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part N includes the task: Z6A.17, Z6B.17 “Connection to the district heating network of the building at Piłsudskiego Street 2a-4b in Bytom”.
The scope of construction works includes the construction of a district heating network approx.2.0 m and the construction of 1 heat node
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part OThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part O includes the task: Z6A.18, Z6B.18 “Attachment to the district heating network of the building at 21 Kosynierów Street in Bytom”.
The scope of construction works includes the construction of a district heating network of approx. 106.0 m and the construction of 1 heat node
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part PThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part P includes the task: Z6A.19, Z6B.19 “Connection to the district heating network of the building at 19 Far Street in Bytom”.
The scope of construction works includes the construction of a heating network of approximately 48.0 m and the construction of 1 heat node
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part BThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part B includes the task: Z6A.2, Z6B.2 “Attachment to the district heating network of buildings in the area of Małachowski and Zabrzańska Street in Bytom”.
The scope of construction works includes the construction of district heating networks approx. 442.0 m and the construction of 8 heat nodes;
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part CThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part C includes the task: Z6A.3, Z6B.3 “Attachment to the district heating network of buildings in the region of Kossaka and Lenartowicz Street in Bytom”.
The scope of construction works includes the construction of district heating networks approx. 132.0 m and the construction of 2 heat nodes;
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part DThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part D includes the task: Z6A.4, Z6B.4 “Attachment to the district heating network of buildings in the area of Sokoła, Matejki, Piłsudski Street in Bytom”.
The scope of construction works includes the construction of district heating networks approx. 245.8 m and the construction of 3 heat nodes;
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part EThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part E includes the task: Z6A.5, Z6B.5 “Attachment to the district heating network of buildings in the area of Grunwaldzki Square and Murarska Street in Bytom”.
The scope of construction works includes the construction of an external receiving system, together with a measuring and clearing system of approximately 6.0 m.
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part FThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part F includes the task: Z6A.6, Z6B.6 “Attachment to the district heating network of buildings in the area of Constitutional Street, Falista, Miechowicka, Kołłątaja in Bytom”.
The scope of construction works includes the construction of a district heating network of approximately 762.3 m and the construction of 8 heat nodes
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part GThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part G includes the task: Z6A.8, Z6B.8 “Attachment to the district heating network of buildings in the area of Judicial Street in Bytom”.
The scope of construction works includes the construction of a district heating network of approx. 5.40 m and the construction of 1 heat node
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part HThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part H includes the task: Z6A.11, Z6B.11 “Connection to the district heating network of the building at 28 Krakowska Street in Bytom”.
The scope of construction works includes the construction of a district heating network of approximately 90.0 m and the construction of 1 heat node
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.
“Liquidation of low emissions in Bytom city in 2020-2021" - Contract IV — Construction of district heating networks (2021) - Part IThe subject of this contract is construction works in the framework of the project “Decommissioning of low emissions in the territory of Bytom in the years 2020-2021" - Contract IV — Construction of district heating networks (2021).
Part I includes the task: Z6A.12, Z6B.12 “Attachment to the district heating network of the building at 4 Siemiradzkiego Street in Bytom”.
The scope of construction works includes the construction of a heating network of approx. 4.5 m and the construction of 1 heat node
A detailed description of the item of the order is contained in Part II of the SWZ — OPZ, together with the annexes.
Order execution dates.
1. The Parties shall set the following dates for the implementation of the subject of the
(a) The commencement of construction works will occur no later than 7 days after the acquisition of the construction site.
(b) The supply of the material shall be reported for receipt after the acquisition of the construction site and after the conditions laid down in the ZPK are fulfilled.
(c) Technological work enabling heat to customers should be carried out and reported for reception (the scope of technological work is specified in the ZPK) by 15 October 2021.
(d) Final work must be carried out and reported for receipt: by 15 December 2021.
e) Completion of the subject matter of the contract — up to 7 months after the conclusion of the contract.
2. The Contracting Authority shall set a time limit for the commencement of reception activities and notify the contractor in writing or e-mail form up to 5 days from the date of receipt of the notification, indicating the place and date of commencement of the receipt of the notification.
3. The Contractor shall be drawn up by the Contractor:
(a) a protocol without comments - the basis for invoice issuing,
(b) the Notes Protocol - not constituting a basis for invoice, not resulting in the accrual of contractual penalties,
(c) a negative result protocol - not a basis for invoice issuing, resulting in contractual penalties after exceeding the deadlines of implementation.