The order was divided into 4 (four) parts, each constituting a self-ordered order. The Contractor may submit a tender for any part or part or for the entire subject of the contract.
1) Part I of the order — Maintenance of the large load truck Jelcz 862 D.43 with the same loading system Multilift MK IV — pcs. 3;
2) Part II of the order — Maintenance of the car large load capacity enlarged Jelcz S662 D.43 — pcs. 1;
3) Part III of the order — Main overhaul of 2 general purpose cars of the average capacity Star 12.220 — pcs. 2;
4) Part IV of the order — Maintenance of the main passenger buses Autosan A10-10T — pcs. 2
Main overhaul of heavy duty trucks Jelcz 862 D.43 with same loading system Multilift MK IVMain overhaul of the Jelcz 862 D.43 large payload system with Multilift MK IV - pcs. 3. Main renovation should ensure the restoration of full technical efficiency of all assemblies, components, mechanisms and equipment installed in the car and recreate the full technical efficiency of all assemblies, components, mechanisms and equipment installed in the car. resourcing for further use to achieve at least the planned target mileage (300,000 km).
Overhaul of the main car with large payload of enlarged mobility Jelcz S662 D.43Overhaul of the main car large load capacity enlarged Jelcz S662 D.43 mobility — pcs. 1. The main renovation should ensure the restoration of full technical efficiency of all assemblies, components, mechanisms and equipment installed in the car and recreate the interrepair resours in dimension 90 000 km to the next main renovation.
Main Overhaul of 2 General Purpose Car Medium Load Star 12.220Main overhaul of 2 general purpose cars of the average load capacity Star 12.220 — pcs. 2. Main renovations should ensure the restoration of full technical efficiency of all assemblies, components, mechanisms and equipment mounted
In the car and recreate resourcing for further use to achieve at least the planned target mileage (250,000 km).
Main overhaul of Autosan A10-10T passenger busesMain renovation of Autosan A10-10T passenger buses — pcs. 2. Main renovation should ensure the restoration of full technical efficiency of all assemblies, components, mechanisms and equipment installed
On the bus and recreate the mileage resours by min. 250,000 km.