After completion of the first construction phase, the extension of the middle school (MS) is now taking place in a second construction phase, an increase in
of existing parts, as well as addition of various areas and construction of a break hall between the new building, the gymnasium
and middle school. In addition, the collection of the middle school is to be completely refurbished. For this purpose, the building will be completely
cleared.
masses:
In the course of the energetic renovation of the middle school in Germering, locksmith work is necessary and carried out in various areas of the project.
The following services are advertised:
- Stair railing (horizontal and inclined) as flat steel bar railing approx. 90 linear meters
- Handrails as round tube on wall approx. 75 linear meters
- Roof ventilation hood on auditorium roof, overall dimension approx. 7.20 x 1.45 x 0.85 m (l x w x h)
- Two exterior sheet metal doors
- Glass parapet in staircase, approx. 8 linear meters
- Steel staircase with pedestal in the interior roof exit
- Steel staircase roof over attic outdoor area
Events:
W+M Planning: 25.07.2022 - 12.08.2022
Montagebeginn: 05.09.2022
Completion: 03.10.2022