Carpentry work inside door construction phase 1-3.
Extension, conversion and general renovation of the Parsberg grammar school in 4 construction phases:
Carpenter interior doors:
- wooden doors type 1: approx. 61 pieces,
- Window sill inside BA 1: approx. 200 m,
- wooden doors type 2: approx. 59 pieces,
- Window sill inside BA 2: approx. 285 m,
- wooden doors BA 3: approx. 64 pieces,
- Window sill inside BA 3: approx. 295 m.
Performance dates:
- Start of assembly BA 1 planned: 25.10.2021,
- Completion date BA 1 planned: 6.5.2022,
- Start of assembly BA 2 and BA 3: after the service request,
- Completion of total output planned: April 30, 2025.