New construction of a children's home with multifunctional event and office space in Unterhaching.
The entire building has a basement, and part of it is an underground car park.
Gross floor area 5,000 m
A recycling center is being built in the front area.
Performance of the service: interior doors.
- 27 St. interior doors, 1- u. 2-leaf, 2.75 m high, steel frame SUZ partly glazed with skylight partly with top panels, solid chipboard door HPL surface, partly. Fire protection requirement;
- 100 St. interior doors, 1- u. 2-leaf, 2.135 m high, steel frame, solid chipboard door HPL surface, tw. Fire protection requirement;
- 3 pcs inner doors, 2.135 m high, steel block frame SBZ, solid chipboard door HPL surface, partly. Fire protection requirement;
- 3 pcs inner doors, 2.135 m high, steel front frame SVZ, solid chipboard door HPL surface, tw. Fire protection requirement;
- 13 pcs inner doors, tubular frame doors aluminum, powder-coated, tw. as fire protection doors T30-RS, elements 1- u. 2-leaf with skylight and tw. with side panel fixed;
- 7 escape door controls;
- Start of execution: 20.5.2020;
- End of execution: 6.4.2021.
Appointments:
- Set-up time, measurement, planning and production: May 20, 2020 - January 5, 2021;
- Execution on site: from 11.1.2021;
- Interior doors on the ground floor + 1st floor: 25.1.2021-25.2.2021.