Replacement of Soulom Low Drop Penstocks
1. Detailed execution studies
2. Site facilities, means(s) of access and handling(s) necessary for the carrying out of the work
3. Removal and Laying of existing penstocks, associated civil works
4. Installation, supply and installation of guard valves
4. Waste management, site cleaning.
5. General coordination of the construction site"