The city of Memmingen, Stadtwerke Memmingen, is planning to build a new combined indoor and outdoor swimming pool as a year-round swimming pool. The entire building is designed and planned as a passive house. All construction structures meet the requirements of a passive house and are designed in close coordination with the
Building physics hit. The new building is to be built on the site of the existing outdoor swimming pool, after demolition of the existing building. The new combined pool includes a 25-meter swimming pool with 8 lanes, a diving board 1 meter / 3 meter, a teaching pool with approx. 12.5 x 10 meters, a course pool with movable floor, a toddler pool, as well as other attractions. In the area of the outdoor pool, a 50-meter pool with 6 lanes, a non-swimmer pool with approx. 500 m² with various attractions and a toddler pool with approx. 100 m² are being built. In addition, a beach volleyball court, a playground and the like, outbuildings with changing rooms, sanitary facilities and a kiosk will be built in the outdoor facilities
Sequence of works:
4 planned work units:
- 1 unit, indoor swimming pool
- 2 units, outdoor pool and garage
- 3 units, pool foundations, lifeguard outdoor pool
- 4 AE, retaining wall, transformer
Main masses indoor swimming pool
earthworks:
- Hinterfüllen Liefermaterial - 1.683 m3
- Fine surface level - 1,297 m2
Concrete and reinforced concrete works:
- WU floor slab - 1,680 m3
- WU exterior wall - 343 m3
- Stahlbetonwände SB3 - 500 m3
- Stahlbetondecken - 1.470 m3
- Formwork walls SB3 - 1,700 m2
- Formwork ceilings - 5,300 m2
- Betonstabstahl 470 t
- Betonstahlmatten - 85 t
- Frischbetonverbundfolie - 1.560 m2
Insulation and waterproofing work:
- Perimeter insulation floor slab - 3,700 m2
- Perimeter insulation wall - 1,300 m2
Masonry work:
- Interior wall sand-lime brick - 170 m2
drainage
- Channel DN 100 - 835 m
- Channel DN 125 - 30 m
- Duct DN 160 - 120 m
- Grease trap NS4 - 1 piece
Inserts ventilation
- Inserts façade ventilation - 96 pieces
Main masses outdoor pool:
earthworks:
- Hinterfüllen Liefermaterial - 580 m3
Concrete and reinforced concrete work:
- Stahlbetonbodenplatte - 66 m3
- Stahlbetonwände S0 - 110 m3
- Formwork walls S0 - 770 m2
- Betonstabstahl - 25 t
- Betonstahlmatten - 16 t
For a detailed description of the trade, see service description
Scheduled schedule:
Start of work within 12 working days after receipt of the request by the client (§ 5 paragraph 2 sentence 2 VOB/B). The request is expected to be received by week 30/2023. The service must be completed (ready for acceptance) within 520 working days after the above-mentioned deadline for the start of execution.
Period of construction work for the indoor swimming pool: 08.2023 – 09.2024
Period of construction work outdoor swimming pool/outbuilding: 09.2024 - 05.2025