In the course of the energetic modernization of component [BC] of the craft campus of the Hanover Chamber of Crafts in Garbsen, tile work is carried out in component [C] and in the atrium. This work includes both wall and floor tiles, including ancillary work. The work will be carried out in 2 stages.
Execution period
BT C: approx. Week 13/2021, 29.3.2021 to week 26/2021, 30.6.2021
Atrium: approx. Week 28/2021, July 14, 2021 to week 35/2021, August 31, 2021.
The tendered services include preliminary and ancillary work for laying floor and wall tiles, including seals, joints, silicone joints, delivery of corner rails, etc. in the components [C] and atrium.
The work will be carried out with a time delay.
Services in sanitary units, public toilet units, storage and technical rooms, as well as corridors and lounge areas:
- Floor tiles total approx. 725 m
- Base tiles total approx. 280 running meters,
- Wall tiles total approx. 990 m
- total silicone joints approx. 560 running meters,
- Work on shower trays 34 pieces,
- cleaning floor surfaces,
- Waterproofing wall surfaces.