As part of the BLB Quick-Win Package Sustainability - radiator valves and thermostatic heads in the existing buildings are being replaced (grant number EU23105.1-4 (2)). In order for the replacement to take place, it is necessary to make the radiators accessible and clear.
Campus GrifflenbergFor the clearance work, 2 teams are needed during the execution period.
Each team consists of a relocation specialist and two assistants.
The calculation is based on 20 working days of 8 hours per month.
The journey is to be specified as a lump sum for both teams. It is assumed that a vehicle will be used.
2 months (20 working days x 2) = 40 working days / x 8h = 320h
2x Umzugsfachkraft = 640h
4x assistant = 1280h
40x Directions
Campus FreudenbergA team is required for the clearance work during the execution period.
The team consists of a relocation specialist and two assistants.
The calculation is based on 20 working days of 8 hours per month.
The journey is to be specified as a lump sum for both teams. It is assumed that a vehicle will be used.
2 months (20 working days x 2) = 40 working days / x 8h = 320h
1x Umzugsfachkraft = 320h
2x assistant = 640h
40x Directions
Campus HaspelA team is needed for the clearance work during the execution period.
The team consists of a relocation specialist and an assistant.
The calculation is based on 20 working days of 8 hours per month.
The journey is to be specified as a lump sum for the team.
It is assumed that a vehicle will be used.
1 month (20 working days) / x 8h = 480h
1x Umzugsfachkraft = 480h
1x assistant = 480h
20x Directions
The execution period is 1 month, the start of power is between the 34th-36th week (21.08.23-08.09.23).