The subject of this order is the execution of construction works on the section of Bodzechów — Sandomierz as part of the project “Works on the railway line no. 25 on the section of Skarżysko Kamienna — Sandomierz”
Full name of the proceedings:
CONSTRUCTION WORKS ON THE SECTION OF THE BODZECHÓW — SANDOMIERZ IN THE FRAMEWORK OF THE PROJECT “WORKS ON THE RAILWAY LINE NO. 25 ON THE SECTION OF SKARŻYSKO KAMIENNA - SANDOMIERZ” IMPLEMENTED IN THE FRAMEWORK OF THE OPERATIONAL PROGRAMME POLISH EASTERN 2014-2020.
The subject of this order is the execution of construction works on the section of Bodzechów — Sandomierz.
The basic scope of the Order includes:
• Works on engineering facilities in track 1 in km: 236,555 and 240,127;
• Works on fifteen engineering facilities in track 1 and 2 in km: 203,624; 205,812; 206,052; 206,063; 207,060; 211,233; 212,111; 213,162; 215,415; 224,866; 226,213; 227,903; 228,514; 228,760; 231,760; 231,760; 62;
• Construction of the road in Brody Municipality over a length of about 460 m.
Option Law 1 includes:
• Works (renovation, reconstruction, maintenance) on twenty-five engineering facilities (in km 201,697; 206,745; 208,337; 208,667; 212,432; 213,782; 214,293; 214,822; 216,448; 216,726; 216,943; 217,220; 218,858; 220,027; 225,238; 225,914; 226,425; 226,853; 227,298; 228,240; 230,966; 232,650; 233,080 ; 233,814; 234,954) in Circuit 2.
Option Law 2 includes:
• Works (renovation) on the engineering facility — bridge on the river Wisła in km 235,682 in track number 1.
The entire subject of the Order includes the implementation of the following elements:
1. Implementation of works in the ranges:
1) pavement and undertrack,
2) catenary with power supply,
3) electrical power equipment and systems up to 1 kV,
4) engineering facilities,
5) geology.
2. Implementation of works involving the construction of environmental protection facilities.
3. Post-built documentation, including:
• the development of technical regulations, in cooperation with the Ordering Party, on the basis of Instructions Ir-3, after completion of construction works, in the scope of all industries,
• development of surveying post-built documentation:
- line picketing and longitudinal profile of the railway line,
- the protocols for passing and receiving of the track axis adjustment signs,
- a numerical situation and altitude map with surveying post-built inventory,
• the development of documentation from the foundation and measurement of the Railway primary surveying and the Railway special warp,
• the development of new diagrams of traffic stations and expeditionary points.
A detailed description of the item of the order is presented in Volume III, IV and V of SWZ.