Geothermal project 19057 Schwerin-Lankow - wellhead and pump riser as well as deep pump installation
The head of the conveyor hole must be gastight for the installation of the deep pump (API standard, pressure stage 3000 PSI = 210 bar). The pump cableoutlet is realized by means of a special wellhead penetrator. Upper transition flange on DN 200 PN 10 for connection to the underground plant.
The offer also includes the supply and installation of a pump riser GRP DN 150 with tensile strength plug-in socket connectors (ZSM) and corresponding transitions to the pump head (bottom) and the casing hanger (above). The installation work can be carried out either by winch or crane (bidder information).