This Tender Guideline concerns a European procedure, in accordance with the ARW 2016, chapter 2, concerning the Gelderland Rail Terminal project in Valburg in the municipality of Overbetuwe. The project consists of two lots:
Lot 1 Preparing for construction at Rail Terminal Gelderland
Lot 2 Access road and landscaping
The work of cutlery B2489-1 consists mainly of:
- Removal of green areas;
- Removal of street furniture;
- Removal of element and asphalt pavements;
- Removal of sewers and culverts;
- Carrying out earthworks and pre-loads;
- Installation of sewerage and culvert works;
- The installation of civil engineering works, including screen screens and covers;
- Taking occupational hygiene measures, safety measures and setting up work areas;
- taking traffic measures;
- Working in a general nature;
- Carrying out preparatory and additional work;
The work of cutlery B2489-2 consists mainly of:
- Removal of green areas;
- Removal of street furniture;
- Removal of element and asphalt pavements;
- Removal of sewers and culverts;
- Carrying out earthworks;
- Carrying out soil remediation;
- Carrying out demolition work;
- Installation of sewerage and culvert works;
- Installation of foundations;
- Installation of element and asphalt pavements;
- Installation of road markings and street furniture;
- Removal and installation of public lighting (by third parties);
- Taking occupational hygiene measures, safety measures and setting up work areas;
- Setting up the remediation site;
- taking traffic measures;
- Working in a general nature.
- Carrying out preparatory and additional work;
- Installation of a traffic control system:
a. the delivery, installation and turnkey delivery of 1 traffic control machine (iVRI-ready,
low voltage 42V suitable for LED class II);
c. the delivery, installation and delivery of the complete road furniture ready for use;
d. the delivery, laying and delivery of all necessary ground cables and pipelines ready for operation;
e. grinding and connecting a complete detection field;
f. performing an (i)Factory Acceptance Test FAT;
g. performing an (i)Site Acceptance Test SAT;
h. the maintenance of the work delivered for 52 weeks after completion;