- The construction of the technical basement, an associated central block with sanitary and administrative part. This volume also includes the centrally located lift of the site.
- Construction of the indoor playground/sports room.
- The entire second school building (ground floor, first floor and technical
spaces).
- Construction of the complete connection passerelle.
- At this stage, it is assumed that the access road to Aquafin has been achieved
and that the road to the silt basin has been finalized. As a result, we are also
project the fire road with associated set-up locations permanently built.
- The extension of the associated bicycle storage part second phase (temporary
position).
- Part of the surrounding construction around the buildings realised.
- The construction of the technical basement, an associated central block with sanitary and administrative part. This volume also includes the centrally located lift of the site.
- Construction of the indoor playground/sports room.
- The entire second school building (ground floor, first floor and technical
spaces).
- Construction of the complete connection passerelle.
- At this stage, it is assumed that the access road to Aquafin has been achieved
and that the road to the silt basin has been finalized. As a result, we are also
project the fire road with associated set-up locations permanently built.
- The extension of the associated bicycle storage part second phase (temporary
position).
- Part of the surrounding construction around the buildings realised.