Parts of furnace burners, furnaces or ovens | Tenderlake

Parts of furnace burners, furnaces or ovens

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
28 November 2023
Closing Date:
04 January 2024
Location(s):
PL921 Radomski (PL Poland/POLSKA)
Description:
Supply of pressure elements for the modernization of the boiler of Unit No. 5 in 2024.

The subject of the Order is "Supply of pressure elements for the needs of modernization of the boiler of Unit No. 5 in 2024" in the period from the date of signing the contract to May 24, 2024, divided into 3 (three) parts

described in detail in Part 2 of the SWZ (Model Agreement).

The Contractor shall fulfil the order under the terms and conditions described in the Model Agreement, part 2 of the SWZ.

Supply of pressure elements for the modernization of the boiler of Unit No. 5 in 2024.

The subject of the Contract is "Supply of pressure elements for the needs of the modernization of the boiler of Unit No. 5 in 2024" in the period from the date of signing the contract to May 24, 2024 as detailed below:

Lp. Description of the object of delivery Quantity IU

1. Elements connecting bulkheads with pairs of the second degree of primary steam superheater according to Fig. No. 3-1456173, item Fig. No. 2 – 7 pcs. In terms of acceptance of the Office of Technical Inspection (UDT) at the workshop, the so-called construction test. 1 set

2. Delivery of the lower section of the second stage of the primary steam superheater, pipe Ø 31.8 x 6.3 fig. no. 2-1456168 item no. 1, 14 pcs.) – bulkheads no. 1 to 14. In terms of acceptance of the Office of Technical Inspection (UDT) at the workshop, the so-called construction test. 1 set

3. Lower elbows of the second degree of the primary steam superheater, drawing no. 3-1456169, item drawing no. 1 and 2, elbows should be extended with straighteners on the inlet side pipe Ø 31.8 x 4, 13CrMo4-5 and outlet pipe Ø 31.8x6.3 10CrMo9-10 to item 42.100 (weld approx. 200mm above the upper hooks) - bulkheads no. 1 to 14. Within the scope of UDT acceptance on

workshop, the so-called construction test. 1 set

4. Delivery of lower elbows of the second stage superheater of secondary steam boilers of 200MW units, item 1 according to documentation No. 2-1450454. Pipe ø 51x5, grade 10CrMo9-10. Straight sections (dimensions c and d) should be extended by 100 mm in relation to the dimensions given in the documentation. Note: Inlet parts of the bent pipe, item 1 secure

by thermal spraying with a coating resistant to low-oxygen corrosion, on the section: on the vertical part before the knee upwards - 1000 mm, knee arch with the oblique part behind the knee - 500 mm. The total area of protection will be 28 pipes x 1500 mm x 3.14 x 51 mm = ~ 7m2. Warranty for coating min. 36

Months. 28 pcs.

5. Single elbow on both sides of the rear wall of the shaft (tube ø 57 x 5.6 grade 16Mo3) of the OP 650 boiler. Item. 1 + item 3 acc. to Fig. 0-1445030, in the amount of 170 pcs. Bending angle 30°, radius R=300mm. 90 pcs.

Comments:

a. Knees should have straight lengths: L1 (upper shoulder) = 250 mm, L2 (lower shoulder) = 500 mm. Bevelled tips,

b. Fins 6mm thick, 8mm wide, chamfered outwards, tube pitch 75mm according to Fig. 0-1445030 cross-section A-A.

c. Within the scope of acceptance of the Office of Technical Inspection (UDT) at the workshop, the so-called construction test.

6. Slag hopper elbows item 1 fig. no. 0-1445034. In terms of acceptance of the Office of Technical Inspection (UDT) at the workshop, the so-called construction test. 50 pcs.

7. Slag hopper elbows item 2 fig no. 0-1445034. In terms of acceptance of the Office of Technical Inspection (UDT) at the workshop, the so-called construction test. 50 pcs.

Supply of pressure elements for the modernization of the boiler of Unit No. 5 in 2024.

The subject of the Contract is the "Supply of pressure elements for the needs of the modernization of the boiler of Unit No. 5 in 2024" in the period from the date of signing the contract to May 24, 2024 as detailed below:

Lp. Description of the object of delivery Quantity IU

1. Screen panel ø57x5,6, grade 16Mo3, pitch 75mm - single-tube, length = 4000mm according to drawing no. 0_1443293. In terms of acceptance of the Office of Technical Inspection (UDT) at the workshop, the so-called construction test. 18 pcs.

2. Screen panel ø57x5,6, grade 16Mo3, pitch 75mm - twin-tube, length = 6000mm according to drawing no. 0_1443293. In terms of acceptance of the Office of Technical Inspection (UDT) at the workshop, the so-called construction test. 49 pcs.

3. Delivery of a welded forged square 225/225/225/225 to be installed on a fresh steam pipeline 2 x ø323,9x40/ 2 x ø323,9,1x40 (mixer built at the level of +29,730m.) 1 pc.

Currently, the mounted square is made of cast steel grade L21HMF according to the attached sketch no. 2.

Calculation parameters of the fresh steam pipeline operation:

pressure – 13,925 MPa,

Temperature – 540 °C,

Operating parameters of the fresh steam pipeline:

pressure – 13,533 MPa,

Temperature – 540 °C,

Within the scope of preparation and agreement in the Office of Technical Inspection (UDT) of the workshop and assembly documentation for the boiler of unit No. 5. - the square must be tested in accordance with PN-EN 10222-2, - the tetrapod must be tested under creep conditions, i.e. simulation PWHT + UTkl3 + Ret (550°C) + x200 and x500 replicas, - Certificate

3.2 for the finished product.

4. Delivery of a forged welded tee 508/356/508 to be installed on the ø508x16/355,6x16 secondary steam pipeline. 10CrMo9-10 (outlet for safety valves) - pcs. 2. Currently, the built-in tees are made in a welded version with reinforcing overlays according to the attached sketch. 1 pc.

Remark! The offer should be accompanied by a conceptual drawing of the forged welded tee.

Calculation parameters of secondary steam pipeline operation:

pressure – 2.84 MPa,

Temperature – 540 °C,

Operating parameters of the fresh steam pipeline:

pressure – 2.35 MPa,

Temperature – 540 °C,

In the scope of execution, acceptance and agreement in the Office of Technical Inspection (UDT) of the workshop and assembly documentation for unit no. 5.

The Ordering Party requires tests to be carried out in accordance with PN-EN 10222-2, and in addition, the tees are to be tested in creep conditions, i.e. simulation PWHT + UTkl.3 + Ret (550°C). C) + x200 and x500 replicas. Certificate 3.2 required for finished product.

Supply of pressure elements for the modernization of the boiler of Unit No. 5 in 2024.

The subject of the Contract is "Supply of pressure elements for the needs of the modernization of the boiler of Unit No. 5 in 2024" in the period from the date of signing the contract to May 24, 2024 as detailed below:

Lp. Description of the object of delivery Quantity IU

1. Supply of straight pipes ø31.8x6.3 grade X10CrMoVNb9-1 in sections L=6200mm in the amount of 36 pieces. The pipes are protected with an anti-erosion coating made in thermal spray technology. Each pipe is protected in two lengths, i.e. from 50mm to 2050mm, and from 3500mm to 5600mm. 36 pcs.

Coating requirements:

- high resistance to ash erosion, corrosion and thermal shocks,

- maintaining protective properties at temperatures up to 900°C,

- adhesion > 45 MPa,

- required coating thickness of at least 500μm after spraying,

- sealed coating,

- no influence of the coating technology on the structure and strength properties of boiler tubes, the structure of the pipe remains unchanged, no remaining thermal stresses.

2. Supply of straight pipes ø31.8x6.3 grade X10CrMoVNb9-1 in sections L=6200mm. 30 pcs.

3. Ø31.8 x 5.6 pipe, grade 13CrMo4-5, 2 m.b. long, with anti-erosion coating made in ARC thermal spray technology. 312 pcs.

Coating requirements:

- high resistance to ash erosion, corrosion and thermal shocks,

- maintaining protective properties at temperatures up to 900°C,

- adhesion > 45 MPa,

- required coating thickness of at least 500μm after spraying,

- sealed coating

- no influence of the coating technology on the structure and strength properties of the boiler tubes, the structure of the pipe remains unchanged, no remaining thermal stresses, - warranty 24 months from the date of delivery

4. Supply of pipe ø324x40mm, grade 14MoV6-3, length L=2000mm 1pc.

5. Supply of pipe ø508x16mm, grade 10CrMo9-10, length L=2000mm 1pc.

6. Supply of straight pipes ø31.8x6.3 grade 10CrMo9-10 in sections L=8000mm 15 pcs.

7. Supply of straight pipes ø51x4 grade 13CrMo4-5 in sections L=6000mm 15 pcs.

8. Supply of straight pipes ø51x4 grade 10CrMo9-10 in sections L=4500mm 30 pcs.

Download full details as .pdf
The Buyer:
Enea Wytwarzanie sp. z o.o.
CPV Code(s):
42390000 - Parts of furnace burners, furnaces or ovens