Renovation of Merkel'sches Schwimmbad Esslingen:
The GFA is approx. 3,000 m² and the BRI 12,000 m³.
The following measures are to be carried out as part of the upcoming renovation:
- Complete renovation of the sports pool and the indoor swimming pool
- Renewal of the technical equipment
- fire protection upgrading
- Barrier-free access
The work will be carried out from September 2023 to December 2024.
Ventilation and air-conditioning systems and I&C technology:
- Dismantling best. Installations
- approx. 1400 m² air duct network, angular
- ca. 400 m Wickelfalzrohr
- ca. 10 Brandschutzklappen
- ca. 25 Volumenstromregler
- ca. 70 Auslässe
- 3x Zentrallüftungsgeräte
- 2x air conditioning split system 5.0 kW
- MSR for HLS