New construction of a residential complex on the Grundfeld in Haimhausen consisting of 3 houses with 3 floors each and a shared underground car park and cellar rooms. A total of 42 residential units will be created, including 30 publicly funded apartments and 12 condominiums.
- Raw installations (laying systems, pipe networks):
40 working days per building
- Ready-made installations (distributions, installation devices, commissioning):
20 working days per building
- Tests, rework, documentation:
15 working days per building
- Further remaining work (close fire protection etc.)
In each case upon request.
If necessary, assemblies must be carried out in several buildings at the same time.
The personnel and machine capacities are the requirements of scheduling
To adapt.
3.2.2021.