The subject of the contract is the development of design and formal and legal documentation related to the implementation of the following task:
"Reconstruction of the gas network with gas connections in m. Lutoryż III'
A detailed description of the subject matter of the contract and the conditions for the execution of the contract shall be included in the template of Annex 2 to the SWZ, together with the annexes thereto.
The subject of the contract is the development of design and formal and legal documentation related to the implementation of the following task:
"Reconstruction of the gas network with gas connections in m. Lutoryż III'
(a) Obtaining discharge and extraction from the land records of the property on which the proposed gas pipeline will be located, together with the accompanying infrastructure
(to the extent necessary to carry out the task).
b) Making maps for design purposes.
c) Obtaining excerpts from the Local Spatial Development Plan or, in the absence thereof, obtaining a decision for the Ordering Party to determine the location of a public purpose investment.
d) Obtaining the consent of the owners of all real estate (or persons legally sanctioned to dispose of the property) to enter the area and permanently seize the property for the purposes of the investment along with consent to the necessary felling of trees and shrubs (in such a case).
e) Development of a construction project constituting, in accordance with the Construction Law, the basis for obtaining a building permit decision or notification of works that do not require a building permit decision, including:
- land development project – 3 copies for the Ordering Party + electronic version on CD.
- architectural and construction design – 3 copies for the Ordering Party + electronic version on CD.
- technical design – 3 copies for the Ordering Party + electronic version on CD.,
f) Preparation of investor cost estimates of 2 copies for the Ordering Party.
g) Before submitting the documentation for the coordination meeting (if necessary), the location of the route of gas pipelines, dam and discharge systems should be agreed in the territorially appropriate Gas Plant.
h) Obtaining all required opinions, reports, arrangements and decisions, including at the coordination meeting, necessary to obtain a legally valid building permit or a final notification of the reconstruction.
i) Obtaining for and on behalf of the Ordering Party a legally valid building permit or notification.
j) Preparation of an inventory of tall greenery in required cases, together with obtaining a permit to remove trees or shrubs.
k) Preparation of a detailed breakdown of the distribution network broken down by diameter and length.
l) Reporting the state of advancement in accordance with the concluded contract.
m) The material scope is presented in the Technical Conditions for the reconstruction of the gas network no.: PSGJA. ZMSZ.763A.270.714785/18-21 of 01.12.2021
n) The locations of the gas pipelines presented on the map sleepers are indicative routes and the lengths of the planned gas network may change
In the study, however, the above may not be the reason for the Contractor's claims to change the remuneration for performance of the subject