Scope of works, earthworks: 28,000 m³, 0/45 backfill: 46,000 TO, paving stones: 7,400 m
Anticipated start of works May 2021. Duration of works 550 working days.
Scope of work, earthworks: 28,000 m³, 0/45 backfill: 46,000 TO, paving stones for sidewalks: 7.400 m2, asphalt: 3.500 TO, concrete: 700 m³, mixed water pipe DN300: 65 ml, rainwater pipe DN300: 465 ml, DN400 rainwater pipe: 670 ml, DN600 rainwater pipe: 85 ml, DN300 wastewater pipe: 340 ml, DN400 wastewater pipe: 415 ml, DN500 wastewater pipe: 410 ml.
Anticipated start of works May 2021. Duration of works 550 working days.