- 12 network cabinets 42U,
- 5 network distributors up to 15U,
- approx. 28,500 m network and fiber optic cables,
- approx. 370 double data connections,
- 1 pc voice alarm center DIN 14675,
- approx. 300 SAA speakers,
- 1 pc fire alarm system DIN 14675,
- approx. 60 automatic and non-automatic detectors,
- 2 St RWA systems,
- approx. 16,000 m E30 and fire alarm lines,
- Execution in 3 construction phases:
- Completion of BA 1 on June 24th, 2022,
- Completion of BA 2 on July 7th, 2023,
—— Completion of BA 3 on June 28, 2024.
s. II 1.4