GEVAG intends to improve the energy efficiency of GEVAG by using existing waste heat.
increase. It is planned that one clean gas heat exchanger per combustion line will be fed into the
To install flue gas pipes in front of the chimney.
The heat exchangers are installed during the regular overhaul without a total standstill.
The scope of supply is described in detail in Part 5 "Specifications for RG channels" and includes:
essentially, the production of all required RG duct sections, the dismantling of the existing ones,
RG ducts that are no longer required, the installation of the clean gas ducts provided by the customer
Heat exchanger, the assembly of the new duct parts, delivery and assembly of the described
measuring instruments, as well as the insulation and sheet metal of the entire scope of delivery and the
Clean gas heat exchanger. Provision of services for incineration line 1 will take place in April 2024, and the
Incineration line 2 August 2024 according to dates section 1.6.
GEVAG intends to improve the energy efficiency of GEVAG by using existing waste heat.
increase. It is planned that one clean gas heat exchanger per combustion line will be fed into the
To install flue gas pipes in front of the chimney.
The heat exchangers are installed during the regular overhaul without a total standstill.
The scope of supply is described in detail in Part 5 "Specifications for RG channels" and includes:
essentially, the production of all required RG duct sections, the dismantling of the existing ones,
RG ducts that are no longer required, the installation of the clean gas ducts provided by the customer
Heat exchanger, the assembly of the new duct parts, delivery and assembly of the described
measuring instruments, as well as the insulation and sheet metal of the entire scope of delivery and the
Clean gas heat exchanger. Provision of services for incineration line 1 will take place in April 2024, and the
Incineration line 2 August 2024 according to dates section 1.6.