The linoleum flooring work for the practical part of the vocational school Höchstädt (in 2 construction phases) includes the linoleum coverings on cement screed as well as the associated wooden skirting boards with all preparatory work.
The practical part of BA 1a (building height approx. 13.50 m) consists of 3 floors with workshops and classrooms, the delayed BA1b of a single-storey building. As floor coverings, linoleum, coatings, wooden paving and tiles are provided. No linoleum coverings are planned in BA 1b.
Short description:
The linoleum flooring work for the practical part of the vocational school Höchstädt (in 2 construction phases) includes the linoleum coverings on cement screed as well as the associated wooden skirting boards with all preparatory work.
The practical part of BA 1a (building height approx. 13.50 m) consists of 3 floors with workshops and classrooms, the delayed BA1b of a single-storey building. As floor coverings, linoleum, coatings, wooden paving and tiles are provided. No linoleum coverings are planned in BA 1b.
masses:
- Linoleum covering 2.5mm: approx. 2.150m² (BA 1a)
- Skirtings oak: approx. 1,350 m
CPV codes:
45432110 - Bodenverlegearbeiten
45432130-4 - Flooring work
Events:
BA 1a: Mid 4th Quarter 2023 – Mid 1st Quarter 2024 (11.12.23 – 06.02.24)
BA1b: no work