Master builder work LV 013A for construction phase 1
Master builder work LV 013A for construction phase 1
Start April 2024, completion November 2024
Construction site equipment electricity, water, crane
earthwork
Excavation 630 cbm
Hinterfüllen 1.640 cbm
Plan, Verdichten
masonry work
Non-load-bearing partitions 400 sq.m.
concrete work
StB components foundations 950 cbm
StB components walls 650 cbm
External waterproofing 620 m²
Perimeter insulation 1600 sq.m.
Formwork 4,300 m²
StB ceiling tiles 580 cbm
Slab formwork 2,700 m²
Finished parts
Stairs, canopies 25 pcs
Structural steel 160 tons
Electrical work
Sewer work Dirty and rainwater