New installation of the central emergency room on the ground floor and basement with treatment, sanitary and
Adjoining rooms.
In an existing building, the ground floor and basement, with a new floor plan layout and a
Floor area on the ground floor and basement of approx. 800m² each, the complete new installation ready for operation, the
High- and low-voltage system for the new central emergency room.
All regulations and standards in force at the time of acceptance must be complied with.
The building's main low-voltage distribution system needs to be renewed. The people who are interested in it
connected supply lines of the sub-distributions on other floors must be connected to a new
Low-voltage main distribution can be relocated.
In detail, the following are carried out:
- 1 fire alarm system for connection to an existing system.
- 1 nurse call system for connection to an existing system.
- 1 emergency lighting system for connection to an existing system.
- 1 NSHV-AV with feed-in and coupling switch, a total of approx. 6 fields.
- 1 NSHV-SV with feed and coupling switch, a total of approx. 5 fields.
- 1 MSR distribution, a total of approx. 4 fields.
- 3 Etagenverteilung-AV.
- 2 Etagenverteilung-SV.
- 2 IT network distributors
- 1 OP-Sicherheitslichtgerät.
- 1 Inner and outer lightning protection system.
- 1 fiber optic and copper data transmission network.
- 1 Baustromversorgung.