Extension of cantonal road no. 3 over a length of 950 m with various plant management structures and a new building by UF Graf.
The main cubatures are:
Excavation work approx. 19,500 m3 fixed
Surface demolition approx. 2,400 m3 loose
concrete pavement demolition approx. 3,000 m3 loose
Concrete (structural concrete) approx. 550 m3
Formwork approx. 1,400 m2
reinforcement approx. 60 t
Gravel sand unbound mixtures 0/45 approx. 15,800 m3 loose
Broken gravel approx. 4'200 m3 loose
topping approx. 5,800 t
Edge terminations approx. 4,800 m
Road drainage approx. 1,900 m
Large bored piles approx. 600 m
Micro piles approx. 400 m
Nail walls approx. 200 m2
Extension of cantonal road no. 3 over a length of 950 m with various plant management structures and a new building by UF Graf.
The main cubatures are:
Excavation work approx. 19,500 m3 fixed
Surface demolition approx. 2,400 m3 loose
concrete pavement demolition approx. 3,000 m3 loose
Concrete (structural concrete) approx. 550 m3
Formwork approx. 1,400 m2
reinforcement approx. 60 t
Gravel sand unbound mixtures 0/45 approx. 15,800 m3 loose
Broken gravel approx. 4'200 m3 loose
topping approx. 5,800 t
Edge terminations approx. 4,800 m
Road drainage approx. 1,900 m
Large bored piles approx. 600 m
Micro piles approx. 400 m
Nail walls approx. 200 m2