Donauausbau Straubing - Vilshofen, Hochwasserschutz Niederalteich, VE18 - Erd-/Tiefbau - Deiche NiDo, SEEB, SCEI, Rückbau Donaudeich, HWS Wände, Betonbauwerke

The subject of the award is construction work on the existing flood protection system around the village of Niederalteich. The flood protection systems are solid structures and dykes along the Danube and the right bank of the Hengersberger Ohe.

The measures put out to tender here in award unit 18 (VE18) essentially include the following buildings (BW):

- Flood protection dike Seebach SEEB 0+000 to 1+340 (BW1, 2, 3), partly with HWS reinforced concrete (StB) walls

- Flood protection dike SCEI 2+300 to 2+559.6 (BW9)

- Flood protection dike Niederalteich-Donau NIDO 0+000 to 0+345; NIDO 0+352 to 1+528 (BW10, 11, 12, 13, 14,15), partly with cervical spine StB walls

- Bauwerk Stemmtor - Access ferry NIDO 0+345 (BW27)

- Structure sewage pipe DN 600 sewage treatment plant Niederalteich NIDO 1+379 (BW79)

- Deichabtrag (Donaudeich)

-- River-km approx. 2279,352 to 2278,835 and river-km approx. 2278,136 to 2277,095 (BW95) River-km approx. 2277,095 to 2276,790 (BW97)

- Dike removal (on the land side Danube dike)

-- River-km approx. 2278,800 and approx. 2278,150 (BW96)

Earthworks:

- Earth removal/excavation (approx. 57,000 m³)

- Bauwerkshinterfüllung (ca. 1.300 m³)

- Deichschüttung (ca. 59.000 m³)

- Mineral inner seal in dike axis (approx. 2,500 m³)

- Filter material dike (approx. 6,500 m³)

Spundwandarbeiten:

- Construction pit sheet piling with strapping / stiffening (approx. 1,600 m²)

- Shorten steel sheet piling on site (approx. 200 m)

- Drawing of on-site sheet piling (approx. 550 m²)

- Sheet pile wall for inner dike sealing and deep foundation HWS wall (approx. 4,300 m²)

Dewatering:

-Open dewatering system (2 pcs.)

Concrete and reinforced concrete work:

- Sauberkeitsschicht C12/15 (ca. 150 m3)

- Unreinforced concrete scour protection with C12/15 X0 (approx. 220 m³)

- Reinforced concrete (floor slab, wall, ceiling, load distribution plate, head beam) (approx. 1,830 m³)

- Unreinforced concrete with C20/25 XC2 WF (approx. 14 m³)

- Reinforcing steel (approx. 190 t)

- Construct in-situ concrete shafts sewage treatment plant (approx. 2 hours)

stairs:

- Make stairs (approx. 12 block steps)

- Remove and reinstall stairs (approx. 49 block steps)

Road and path construction work:

- Asphaltarbeiten (ca. 6.100 m²)

- Gravel base layers 0/32 mm (asphalt, gravel lawn, water-bound surface) (approx. 4,600 m3)

- Gravel base layers 0/56 mm (gravel lawn, water-bound surface) (approx. 1,900 m3)

- Surface course crushed sand (approx. 6,400 m²)

- Schotterrasen (ca. 4,800 m²)

- High board made of concrete C12/15 (approx. 100 m)

Pipe and pipeline construction work:

- Laying cast iron pipes outlet sewage treatment plant incl. fittings (approx. 35 m)

- Steel protection pipe sewage treatment plant (approx. 21 m)

Demolition and dismantling work:

- Dismantling and demolition of stairs (approx. 4.1 t)

- Dismantling and demolition of reinforced concrete structures (approx. 32 m3)

- Dismantling and demolition of asphalt surfaces (asphalt surface and asphalt base courses) (approx. 1,245 m3)

- Dismantling and demolition of asphalt base course polluted (approx. 145 t)

- Dismantling and demolition of sewage pipes GGG (approx. 40 m)

- Dismantling and demolition of sewage pipe asbestos cement (AZ) (approx. 36 m)

- Dismantling and demolition of narrow wall dike interior seal in the area of the sewage treatment plant (approx. 12 m3)

- Dismantling and demolition of water-bound pavements (approx. 1,695 m²)

Technical processing

- Create construction site layout plan or plans

- Create construction schedule

- Create flood protection concept

- Create quality assurance concept for earthworks and concrete construction

- Create plans for sheet piling (e.g. pile driving plans)

- Planning of shoring class B

- Final measurement and documentation