The subject of the contract is the execution of a construction, executive design and bill of quantities for the reconstruction of the N/C gas network in Krakow, Królowej Jadwigi Street, Grabowa Street, Sarnie Uroczysko Street, Kotlarczyków Street, Nitscha Street, Chwista Street, Baranieckiego Street, Łazarskiego Street. The project should be developed according to Technical Conditions No: PSGKR. ZMSM. 763.1111368.2.21 of 04.07.2022 issued by Polska Spółka Gazownictwa Sp. z o.o., Oddział Zakład Gazowniczy w Krakowie.
The subject of the contract is the execution of a construction, executive design and bill of quantities for the reconstruction of the N/C gas network in Krakow, Królowej Jadwigi Street, Grabowa Street, Sarnie Uroczysko Street, Kotlarczyków Street, Nitscha Street, Chwista Street, Baranieckiego Street, Łazarskiego Street. The project should be developed according to Technical Conditions No: PSGKR. ZMSM. 763.1111368.2.21 of 04.07.2022 issued by Polska Spółka Gazownictwa Sp. z o.o., Oddział Zakład Gazowniczy w Krakowie.
Specifications:
1) type of plant: low pressure gas network,
2) location: Kraków Królowej Jadwigi Street, Grabowa Street, Sarnie Uroczysko Street, Kotlarczyków Street, Nitscha Street, Chwista Street, Baranieckiego Street, Łazarskiego Street,
3) gas network length: 5349m, including:
Gas pipeline:
- 867m PE dn 225,
- 441m PE dn 110,
- 1267m PE dn 90,
gas connections:
- 661m PE dn 90,
- 2113m PE dn 63
(the given length of the planned gas pipeline is an estimated quantity and may change in the event of a change in formal, legal and/or environmental conditions; The Contracting Authority allows an increase in the length of the gas pipeline by 1.5% as part of the Contractor's remuneration); whereby:
a) materiał: PE 100 RC SDR 17,6, PE 100 RC SDR 11,
b) diameter: dn 225, dn 110, dn 90, dn 63,
c) pressure: low.
2. Detailed scope of work:
a) execution of construction, executive design and bill of quantities for the reconstruction of the N/C gas network in Krakow, Królowej Jadwigi Street, Grabowa Street, Sarnie Uroczysko Street, Kotlarczyków Street, Nitscha Street, Chwista Street, Baranieckiego Street, Łazarskiego Street. The project should be developed according to Technical Conditions No: PSGKR. ZMSM. 763.1111368.2.21 of 04.07.2022 issued by Polska Spółka Gazownictwa Sp. z o.o., Oddział Zakład Gazowniczy w Krakowie;
b) development of projects for the reconstruction of construction works interfering with the designed gas network (including, among others: roads, pavements) required by appropriate decisions and arrangements;
c) making the necessary arrangements (and/or obtaining decisions, provisions) with utilities users, owners of land, real estate or competent public administration bodies;
d) agreement with the relevant services, institutions, location offices, conditions for land occupation, restoration, etc. and obtaining the necessary administrative decisions in this respect, if such are required for the implementation of the Agreement;
(e) if necessary, to agree on the designed facilities in the conservation or nature protection zone;
f) obtaining by the Contractor other decisions and arrangements, including at the coordination meeting, which are required by law and necessary to obtain a final building permit or notification of the commencement of works, to which the authority has not objected, in order to enable the implementation of the planned investment;
g) obtaining for and on behalf of the Ordering Party a final decision on the building permit or notification of the commencement of works, to which the authority has not objected.
A detailed description of the subject of the order can be found in Appendix No. 1 to the Agreement.
The conditions for the performance of the contract and the obligations of the Contractor and the Ordering Party in connection with its implementation are specified in the draft Agreement, which constitutes Appendix No. 6 to the SWZ.