Construction work for swimming pool | Tenderlake

Construction work for swimming pool

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
09 November 2020
Closing Date:
03 December 2020
Location(s):
DE124 Rastatt (DE Germany/DEUTSCHLAND)
Description:
Redesign of the Bühlot outdoor pool in Bühlertal - stainless steel pool

Renewal and modernization of the Bühlot outdoor pool in Bühlertal:

After more than 50 years of operation, the outdoor swimming pool built in the 1960s is in need of major renovation and modernization.

The following measures are planned:

- Reduction of the water surface of the existing combination pool from approx. 1,500 square meters to 960 square meters,

- Dismantling of the existing functional building and replacement with a two-part new building with accommodation of the technical systems as well as the changing, sanitary and personnel areas,

- Complete renewal of the water treatment system and the associated piping as well as renewal of the sanitary, heat supply and electrical systems,

- Installation of a stainless steel combination pool in the existing concrete pool,

- complete renovation of the outdoor facilities,

- Installation of a wide wave slide and a new jumping facility (1 m, 3 m, 5 m).

Start of construction: March 1, 2021 Completion: April 15, 2022 Total construction costs (KG 200-600): approx. 5.6 million EUR net.

Stainless steel basin:

- approx. 960 sqm combination pool consisting of:

- swimming pool 25 x 13.5 m with water depths from 1.36 to 1.85 m,

- non-swimmer pools 23 x 21 m with water depths from 0.60 to 1.20 m,

- Diving pool 10.5 x 11.75 m with a water depth of up to 4.00 m.

Service period:

- by KW11 2021: provide construction information for shell construction,

- by week 12 2012: submission of the execution drawings,

- from week 28 2021 to mid-November 2021 assembly of the pools on the construction site.

Download full details as .pdf
The Buyer:
Gemeinde Bühlertal
CPV Code(s):
45212212 - Construction work for swimming pool