Extension of the secondary school Mühldorf a. Inn
the new building complements the existing school building with two further full storeys
Gross volume: 8.867m³
Floor area: 7.179m²
Electrical installations
ca. 650m Hauptleitungen
ca. 850m Verlegesysteme
ca. 250m Unterflurkanalsystem
4 pcs. electrical sub-distributor with knX fittings
15 st. installation columns for classrooms
approx. 25,000m line network of high-voltage power plants
approx. 600 switching, control and plug-in devices
ca. 250St. LED- Einbaudownlights
approx. 260lfm continuous row LED profile luminaires
approx. 390 emergency warning/safety lights
1 hour emergency lighting centre with sub-centres
1 St. ELA/SAA headquarters
approx. 7,500m low-voltage line network
approx. 100 fire alarm field devices with extension of existing fire alarm panel
approx. 90 Pcs. ELA/SAA loudspeakers
approx. 20 secondary clocks with clock centre
1 St. Lichtrufanlage
approx. 500m fiber optic cable
approx. 7,500m data duplex line with data distributor
approx. 10 outdoor luminaires