TRIC A 271 scaffolding work for the general renovation school center Haßfurt - only BA IV - Schulstraße
- work and protective scaffolding for installation facade work
TRIC A 271 scaffolding work for the general renovation school center Haßfurt - only BA IV - Schulstraße
- DIN EN 12811-1 and DIN 4420-1 working and protective scaffolding as a free-standing scaffolding without anchoring to the structure, load class 3, with wall-side covering extension 0.30m and with 2 scaffolding layers, incl. ladder aisles, top layer height approx. 3.50/4.00m for working height max. 5 m to approx. 60m building length, totaling approx. 410m²,
- installation on gravelled terrain including structural bracing and support, planned maintenance approx. 6 weeks
- for execution of façade installation work