New construction of a sewage pressure pipe for the connection of the Ehrang sewage treatment plant to the main sewage treatment plant in Trier,
VE 01 + VE 01.1 + VE 03 Geschlossene Leitungsverlegung,
- Durchpressung Stahlschutzrohr DN800: ca. 35 m
- HDD process Moselle cullet, 2 holes a 460 m, diameter 500mm
- HDD process highway culvert, 2 holes a 60 m, diameter 500mm
- PE pipes da 400: approx. 600m, deliver and lay
- PE pipes da 250: approx. 600m, deliver and lay
- PE pipes da 160: approx. 1,200m, deliver and lay
SWT Trier is planning to connect the Trier-Ehrang wastewater treatment plant to the main sewage treatment plant in Trier.
A new sewage pressure pipe PE da400 and da250, SDR 11 will be laid.
There is a pressing below the B 53 in the steel protection pipe DN 800 as well as 2x HDD boreholes as Moselle culverts and 2x HDD boreholes as motorway culverts.
With the wastewater pressure pipe, an empty pipe DN/OD 160 and a multi-occupancy pipe are also laid.