Special civil engineering work.
- construction site installation bored pile foundation,
- calibration and stakeout work,
- about 950 cbm production of a work plan,
- approx. 105 St. reinforced cast-in-place piles in cased borehole, diameter approx. 0.80 m,
- of which 12 piles are prefabricated and loaded (3 static and 1 dynamic test load) 4 x 1 test load pile plus 2 anchoring piles (Σ = 12 piles),
- individual lengths approx. 12.0 to 14.50 m incl. Pile head,
- carrying out 3 static and 1 dynamic test loadings,
- Disposal and disposal of the flushing and drilling material up to LAGA Z2,
- Dismantling of the work plan for the further use of the material by the A.
In connection with the construction work, the provision of planning services for structural design (approval and execution planning) is also required.
The execution of the service should take place between 11/2019 and 3/2020.