The Mörlenbach valley bridge is part of the planned overall measure B38 OU Mörlenbach, which is led to the east around the town of Mörlenbach. The planned bridge structure will bridge the existing valley of the Mörlenbach with the Lumpenackerweg municipal road running there and the L3120 state road.
As part of this service request, the services of the static and constructive plan review are requested.
For the project mentioned under point II.1.4 of this announcement, the following services have to be performed:
static/constructive design checks
and
welding/corrosion protection design tests
Service period, deadlines:
Start of execution 5 working days after award.
latest start of execution: 31.01.2022
expected completion date: 28.02.2025
Further intermediate dates can be found in the tender documents.