Doemens e. V. intends to build a new training and further education facility with administration. The planned building project is a facility for inter-company vocational training. The objective of the planning is a compact three-story building on Lohenstrasse.
The current tender relates to the outdoor facilities - landscaping.
The essential masses of landscaping work (approx.):
Ground floor outdoor facilities: approx. 3,550 m² of which approx. 270 m² built under roof terraces on the 1st floor: approx. 115 m² earthworks / floor drainage approx. 340 m³ large-format concrete slab covering approx. 1,420 m² water-bound ceiling academy garden approx Wooden construction approx. 40 m lawn paving stones for car parking spaces approx. 415 m² facade channels approx. 45 m drainage channels approx. 18 m underground pipes approx. 150 m precast concrete seat walls approx. 17 m concrete block steps approx. 16 m bar fence 1.20 - 1.40 m approx. 160 m gate, B = 5.00 m approx. 1 handrails approx. 11 m steel frames for raised beds approx. 40 m light foundations approx. 8 flagpoles approx. 3 bicycle brackets approx. 10 top floor / tree substrate Delivery approx 760 m³ tree planting approx. 23 hedges approx. 145 m² planting area (shrubs and perennials) approx. 530 m² lawn or meadow areas approx. 880 m² wooden decking on the 1st floor approx. 115 m² Expected execution dates for construction:
Start: May 3, 2021 Completion: November 30, 2021 Subsequent completion maintenance
Doemens e. V. intends to build a new training and further education facility with administration. The planned building project is a facility for inter-company vocational training. The objective of the planning is a compact three-story building on Lohenstrasse.
The current tender relates to the outdoor facilities - landscaping.
The essential masses of landscaping work (approx.):
Ground floor outdoor facilities: approx. 3,550 m² of which approx. 270 m² built under roof terraces on the 1st floor: approx. 115 m² earthworks / floor drainage approx. 340 m³ large-format concrete slab covering approx. 1,420 m² water-bound ceiling academy garden approx Wooden construction approx. 40 m lawn paving stones for car parking spaces approx. 415 m² facade channels approx. 45 m drainage channels approx. 18 m underground pipes approx. 150 m precast concrete seat walls approx. 17 m concrete block steps approx. 16 m bar fence 1.20 - 1.40 m approx. 160 m gate, B = 5.00 m approx. 1 handrails approx. 11 m steel frames for raised beds approx. 40 m light foundations approx. 8 flagpoles approx. 3 bicycle brackets approx. 10 top floor / tree substrate Delivery approx 760 m³ tree planting approx. 23 hedges approx. 145 m² planting area (shrubs and perennials) approx. 530 m² lawn or meadow areas approx. 880 m² wooden decking on the 1st floor approx. 115 m² Expected execution dates for construction: