The subject of the contract is the performance of the exchange service of direct electricity meters at customers of PGE DISTRIBUTION S.A. BRANCH RZESZÓW. The service also includes notifying customers of the time limit of the exchange and appointing the recipients of the contracting party for a replacement
RE Rzeszów_1: exchange of direct electricity meters in Rzeszów Energy District — Rzeszów city and municipality: Boguchwała, Lubenia, Chmielnik, Błażowa, HyżneNumber of meters to exchange: 11,050 pcs including 1Faz — 5 625 pcs., 3Faz — 5,425 pcs.
RE Stalowa Wola_2: exchange of direct electricity meters in Steel Wola Energy District: PE Janów Lubelski, Annopol, Harasiuki, NiskoNumber of meters to replace: 3,700 pcs, including 1Faz - 851 pcs., 3Phaz. — 2,849 pcs.
RE Krosno_1: exchange of direct electricity meters in the area of Energy District Krosno: PE Krosno, DuklaNumber of meters to exchange: 4,927 pcs, including 1Faz — 1,493 pcs., 3Phaz. — 3,434 pcs.
RE Krosno_2: exchange of direct electricity meters in the area of Energy District Krosno: PE JasłoNumber of meters to exchange: 7,275 pcs, including 1Faz — 1,381 pcs., 3Phaz. — 5,894 pcs.
RE Krosno_3: exchange of direct electricity meters in the area of Energy District Krosno: PE StrzyżówNumber of meters to replace: 5 539 pcs, including 1Phaz — 1,200 pcs., 3Faz — 4,224 pcs.
RE Leżajsk: exchange of direct electricity meters in the Leżajsk Energy DistrictNumber of meters to replace: 5,700 pcs, including 1Phaz — 1,200 pcs., 3Faz — 4,500 pcs.
RE Rzeszów_2: exchange of direct electricity meters in the Rzeszów Energy District — the city of Rzeszów and the municipality of Krasne, Trzebownisko, Głogów Młp., ŚwilczaNumber of meters to exchange: 13,450 pcs, including 1Faz — 7 125 pcs., 3Faz — 6,325 pcs.
RE Mielec_1: exchange of direct electricity meters in Mielec Energy District, PE Kolbuszowa, RopczyceNumber of meters to replace: 6,900 pcs, including 1Phaz — 3,600 pcs., 3Phaz. — 3 300 pcs.
RE Mielec_2: exchange of direct electricity meters in Mielec Energy District: PE Tarnobrzeg, Nowa DębaNumber of meters to replace: 7,100 pcs, including 1Phaz. — 3 800 pcs., 3Phaz. — 3 300 pcs.
RE Staszów_1: exchange of direct electricity meters in the Staszów Energy District: PE Staszów, KlimontówNumber of meters to replace: 3200 pcs., including. 1Phase - 1300 pcs., 3Phaz - 1900 pcs.
RE Staszów_2: exchange of direct electricity meters in Staszów Energy District: PE Sandomierz, Ożarów, OpatówNumber of meters to replace: 3 700 pcs, including 1Phaz - 1700 pcs., 3Faz — 2,000 pcs.
RE Sanok_1: exchange of direct electricity meters in Sanok Energy District: PE Sanok, BrzozówNumber of meters to exchange: 4,700 pcs, including 1Phaz — 2,000 pcs., 3Phaz. — 2,700 pcs.
RE Sanok_2: exchange of direct electricity meters in Sanok Energy District: PE Lesko, Besko, Komańcza, Ustrzyki DolneNumber of meters to replace: 6,300 pcs, including 1Phaz. — 1,500 pcs., 3Phaz. — 4,800 pcs.
RE Stalowa Wola_1: exchange of direct electricity meters in Energy District Stalowa Wola: PE Stalowa WolaNumber of meters to replace: 4,000pcs, including 1Phaz — 4,000 pcs., 3Phaz. — none