Rheinbahn AG is planning to build 2 new bus parking halls (bus carpots) with a car wash, cleaning pit, loading technology and associated technical rooms with a gross volume (BRI) of approx. 42,000 m³ at the Heerdt depot, Kevelaerer Str. 1, 40549 Düsseldorf, during ongoing operations. The subject of the contract to be awarded is the technical lot T 3 TGA - Energy and charging technology (switchgear, transformers, raised floors, chargers and hoods).
Lot T3 - Energy and Charging Technology essentially comprises the electrotechnical development of the two bus carports with the corresponding charging infrastructure. For this purpose, a ring line between the signal box and the central building will be reinforced and ground into a new medium-voltage station to be built.
Lot T3 includes the following services:
- Realization of 60 covered charging spaces (charging by pantograph)
- Mittelspannungsringstation
- 3 Gießharztransformatoren
- Niederspannungsverteilung
For the rest, see the service description provided in the project room.